What five, ten and twenty million yen actually buy
Buy cheap in Japan and just do it up a bit, the forums say. Buying cheap is true. What "a bit" means, and what it costs, is the part nobody writes down.
In short
- Around five million yen makes a house habitable without touching anything structural. Around twenty million replaces everything inside the frame.
- The cost you cannot forecast is what appears once a wall is opened. Budget a contingency of ten to twenty per cent as a matter of course.
- Sequence decides value. New kitchens under a roof that leaks are money spent twice.
What follows assumes an ordinary detached timber house of roughly 80 to 120 square metres. These are orders of magnitude, not estimates, and they exclude the purchase price and its associated costs. Real figures move a great deal with condition, structure, location, specification and contractor.
Around five million yen
This is the floor for making a house liveable. It reaches the fittings and the surfaces. It does not reach the structure.
| Work | Roughly |
|---|---|
| Wet areas | One or two of kitchen, bathroom and lavatory, replaced together |
| Interior finishes | Wallpaper, flooring laid over the existing, tatami re-covered |
| Fittings | Water heater, lighting, sockets and switches |
| Doors | Adjusting or replacing what no longer moves. New locks |
| Cleaning | Professional clean throughout |
What this budget cannot include: roof and exterior wall work, insulation, seismic strengthening, full replacement of supply and waste pipework, replacement of termite-damaged members, or repair to the foundation or frame.
None of the work that extends the life of the building is in reach at this level. The result is a house that looks better and has the same problems. Cheap property plus cheap renovation frequently means paying again a few years later, that time for the structure.
Around ten million yen
Here the structure comes within reach, but not all of it. This budget is about choosing.
| Work | Roughly |
|---|---|
| Wet areas | Kitchen, bathroom, lavatory and basin, all replaced |
| Pipework | Supply and waste, partially or completely renewed |
| Roof or exterior walls | Re-roofing, or exterior coating and local repair. Both to a high standard is difficult |
| Underfloor | Damp proofing, improved ventilation, local reinforcement of sills |
| Interior | Walls, ceilings and floors throughout. Limited changes to the layout |
| Electrical | New consumer unit, additional circuits, increased capacity |
The decision that defines this budget is roof or exterior walls. Both determine the life of the building, and doing both properly at this level is difficult. Take the one in worse condition and leave the other for its next cycle.
Seismic strengthening and insulation rarely both survive that choice. Which of them matters more depends on the building, and which structural rules it was built under is where that assessment starts.
Around twenty million yen
This replaces everything inside the frame. It is close to what people mean by a full renovation.
| Work | Roughly |
|---|---|
| Everything above | Wet areas, pipework, roof, exterior, interior and electrical |
| Seismic strengthening | Following an assessment. Connection hardware, wall reinforcement, foundation repair |
| Insulation | Walls, ceiling and underfloor, with insulated glazing |
| Layout | Removing and adding partitions where the structure allows |
| Accessibility | Removing level changes, handrails, wider openings |
Even here it is not equivalent to a new house. The foundation, columns, beams and parts of the sill remain as they were. Where decay or termite damage means structural members have to be replaced extensively, twenty million can be insufficient, and the honest conclusion is sometimes that building new would be more rational.
Establishing which of those two situations you are in is the job of investigation before purchase, not after demolition begins.
There is a procedural point at this level as well. Since April 2025, work on a two-storey timber house that extends to more than half of a principal structural part, such as the walls, floors or roof, requires building confirmation before it starts. That brings in an architect, drawings, fees and time, and the work is checked against current rules. Whether a given scope crosses that line is a question to settle with the contractor and the municipality before the budget is fixed. On a plot with frontage problems the consequences go further, as set out in the land you can never build on again.
Five things that move the number
| Factor | Effect |
|---|---|
| Width of the road in front | Narrow access restricts deliveries and scaffolding. Time and cost both rise |
| Condition of the building | What is found once it is opened. Every renovation has a part nobody can see in advance |
| Location | Labour rates differ between cities and the countryside, though rural areas may offer fewer contractors to choose from |
| Specification | Fittings and materials move the total several times over. The imagined budget and the chosen specification frequently do not match |
| Contents left behind | Furniture still in the house has to be removed and disposed of before work starts. Routinely omitted from the sums |
The second is the one that cannot be forecast. Open a wall and the insulation is wet. Lift a floor and the sill has been eaten. These are not unusual findings in an old building; they are what old buildings contain. They do not appear in a quotation, because nobody could see them when the quotation was written.
Carry a contingency of ten to twenty per cent. It is not an indulgence, it is the part of the budget that deals with what nobody could see.
What commissioning work from abroad adds
Beyond the work itself, an overseas owner carries costs that appear in no quotation.
- Language. Quotations, contracts and specifications are in Japanese, and so are the meetings. Signing without understanding is a real risk.
- Site presence. You cannot attend during the work or at completion, so you are judging the result from photographs.
- Decisions on variations. When a wall comes open and a cost appears, an answer is wanted immediately, across a time difference, through translation, on the basis of a photograph and a paragraph.
- Payment. Deposit, interim and final payments, each with international transfer timing and fees.
- Choosing the contractor. Judging who is reliable, from another country, with limited means of checking.
Not being in Japan does not change the price of the work. It changes how the work is managed, and that requires somebody on the ground.
Order matters more than budget
This is the part worth taking away from the whole article.
A new kitchen under a roof that admits water is a new kitchen that will be damaged. New wallpaper over a subfloor that is damp lifts within a few years. The same money buys a completely different outcome depending on the order in which it is spent.
- Structure first. Repair leaks, treat termites and replace damaged members, repair sills and foundation.
- Then water: roof and exterior. Until the water is stopped, everything repaired inside continues to be destroyed.
- Then services. Pipework and electrical, because they are behind everything else.
- Then insulation and strengthening. Most efficient while walls are already open.
- Finishes and fittings last. What you can see comes at the end.
Most buyers start at five. The impulse to fix what is visible is entirely understandable. The correct order puts the invisible first, and how the invisible parts fail is set out in by the time it shows on the ceiling, the wood has been wet for a while.
What these figures are not
Nothing here is a quotation or an estimate for any property or any scope of work. The figures are orders of magnitude for an ordinary timber house and vary substantially with condition, structure, location, specification and contractor.
Obtain quotations from several contractors who have inspected the building. En Beau lo does not carry out construction work and introduces contractors where they are needed.
Know what needs doing before you ask what it costs
The number that matters is not the renovation budget. It is the purchase price plus the transaction costs plus the work, and the work cannot be scoped from a listing. What else sits outside the purchase price is set out in what a cheap Japanese house actually costs, and our cost estimator covers the transaction side.
The condition sets the budget, not the other way round
We visit the property, record its condition with photographs, and set out what is likely to need attention and in what order. Where quotations are needed, we introduce contractors and explain what they have written in your language.
Ask us to check a property on siteSources and notes
The figures in this article are general orders of magnitude for a detached timber house of approximately 80 to 120 square metres, drawn from field experience, and are not estimates for any particular property or scope. Actual costs depend on the condition and structure of the building, its location, the work specified, the materials chosen and the contractor engaged.